At 08:41 Aug. 27th, 2012 (local time), 1# unit in Pacitan Project passed 30-day reliable run, with the signing by PT.PLN (Persero)—the Project owner.
 
Since 1# unit entered into 30-day reliable run on July 27th, DEC Project team has dedicated even greater attention and efforts to ensure the unit’s stable running. During this phase, key parameters—average load: 260MW, protective service rate: 100%, automatic service rate: 95%, steam quality: qualified—show excellent condition of the whole unit; in addition, it has operated 96 hours continuously in maximum 315MW load.
 
1# Unit’s success of 30-day reliable run is an important landmark and lays solid foundation for the completion of the whole Project. In the next phase, performance test and the acquisition of TOC will be the Project’s top priority.

At 16:21Sept.6th, 2012 (local time), 2# Unit in Pacitan Project achieved synchronization and ran stably with all parameters being normal.